The government spent R797 million and 15 years on a water supply scheme that is still not complete
The Moutse Bulk Water Supply Scheme in Limpopo has remained incomplete for 15 years, despite the government allocating R797 million to the project.
Construction of the supply scheme began in 2011, with the first phases of the project carried out by private contractors.
These contractors had to be terminated due to poor performance and workmanship, leaving the Department of Water and Sanitation’s (DWS) construction unit to complete the remaining work.
This was revealed by Water and Sanitation Minister Pemmy Majodina in response to a Parliamentary question from National Assembly member Stanley Ramaila.
Ramaila asked the minister what plans her department has put in place to prioritise the long outstanding Groblersdal-Moutse Villages Water Project.
He said completing this project is imperative to provide immediate relief to affected communities, restore their dignity, and demonstrate the government’s commitment to delivering on its promise of water as a basic human right.
In response, Majodina said the Moutse Bulk Water Supply Scheme was initiated to address longstanding water supply challenges in Moutse East and Moutse West.
These areas fall within the Elias Motsoaledi and Ephraim Mogale Local Municipalities, respectively, in the Sekhukhune District Municipality.
To increase access to water and reliability of supply, the government has spent R797 million on the Moutse Bulk Water Supply Scheme.
Upon commissioning, the Moutse Bulk Water Supply Scheme is expected to provide bulk water supply to 40 villages and settlements across Moutse East and Moutse West.
Some of the beneficiaries include Maganagobuswa, Kgobokwane, Walkraal, Naganeng, Ga-Matlala, Stompo, Mpheleng, Mabuyeni, Joe Slovo Park, Magakadimeng, and Moteti.
“The scheme is further intended to reduce reliance on the constrained Western Highveld Water Supply System, which serves the wider region, including areas within the Dr JS Moroka Local Municipality,” Majodina said.
She explained that the project commenced in December 2011 and was funded through the Regional Bulk Infrastructure Grant.
Sekhukhune DM was appointed as the Implementing Agent, and implementation was divided into 15 work packages, grouped into three functional phases.
Each phase was designed to provide immediate water supply benefits upon completion and commissioning.
Where the project went wrong

Majodina explained that the first five work packages on the Moutse project were implemented by private contractors appointed by Sekhukhune DM.
However, these contractors had to be terminated due to poor performance and workmanship.
This means the outstanding works, along with work packages 6 through 15, were transferred to the DWS Construction Unit for reconstruction, remedial work, and commissioning.
“Although most of the bulk infrastructure has been substantially completed, these challenges have prevented the scheme from being fully commissioned and becoming operational,” Majodina said.
“Overall project progress is above 90%, with most work packages completed and ready for commissioning.”
Majodina said the work still to be done on this project primarily concerns mechanical and electrical installations at the Groblersdal WTW and the Groblersdal West Pump Station.
“Progress has also been affected by the theft and vandalism of electrical infrastructure, including incidents of armed robbery involving site security personnel,” she added.
“Replacement of the damaged equipment and completion of the remaining works were scheduled for October 2026.”
Regarding work packages 2 to 5, which the private contractors completed insufficiently, Majodina said they require refurbishment and remedial works.
These packages comprise the bulk pipeline from the Groblersdal WTW to the first booster pump station.
To address these defects and facilitate the commissioning of the overall scheme, Sekhukhune District Municipality initiated a refurbishment project in 2022.
This was done with support from DWS through the Water Services Infrastructure Grant (WSIG).
“The DWS Construction Unit was appointed to undertake the remedial works. These works are currently reported to be 43% complete, with completion anticipated by February 2027,” Majodina said.
Log in or register for free access to all articles.
Conversation
6 commentsUnder Pemmy Majodina’s careful watch the project still has a long way to go.
Many cadres are waiting in line for their share of the loot.