Eleven years, zero megawatts delivered: South Africa’s gas-to-power procurement failure

South Africa’s latest gas-to-power procurement has ended without a single preferred bidder or megawatt awarded. 

The outcome marks another setback in more than a decade of government efforts to procure gas-fired electricity generation from independent power producers (IPPs).

It raises questions about the planning, coordination and implementation of the country’s gas-to-power ambitions, representing another setback for South Africa’s energy plans.

This follows an announcement by Electricity and Energy Minister Kgosientsho Ramokgopa on 28 October 2026. 

Ramokgopa announced that no preferred bidders have been appointed under the first bid window of South Africa’s Gas Independent Power Producer Procurement Programme (GASIPPPP).

The programme sought to procure 2,000 MW of gas-fired electricity generation. Four bids offering 2,830 MW were received by the closing date of 29 May 2026.

These bids demonstrate the substantial interest from IPPs for this programme.

However, after evaluation, none satisfied the mandatory functional criteria, principally because bidders could not provide the required assurances of long-term gas supply.

The result is stark. After more than 11 years of government-led procurement initiatives, South Africa has yet to deliver any new gas-fired IPP generating capacity through its major dedicated gas-to-power procurement programmes.

The question is no longer simply when South Africa will procure new gas-fired generation.

Instead, it has become a question of whether the country’s procurement approach is suited to the infrastructure, fuel supply, and commercial realities facing prospective investors.

South Africa’s modern gas-to-power procurement programme began in May 2015, when the Energy Department issued a Request for Information for 3,000 MW of gas-fired generation.

In October 2016, then-Energy Minister Tina Joemat-Pettersson released a Preliminary Information Memorandum (PIM).

The PIM outlined plans to procure 3,000 MW of liquefied natural gas (LNG) generation capacity.

The proposed programme envisaged 2,000 MW at Richards Bay in KwaZulu-Natal and 1,000 MW at Coega in the Eastern Cape.

It recognised that gas-fired power stations could provide the anchor demand needed to justify investment in LNG import terminals, floating storage and regasification units, pipelines, and associated infrastructure.

Despite extensive preliminary work, consultations, and market interest, the programme never progressed to a formal Request for Proposals (RFP).

No preferred bidders were appointed, no power purchase agreements (PPAs) were signed, and no generating capacity was delivered.

Emergency procurement and the Karpowership controversy

The government’s next significant attempt to introduce gas-fired IPP generation came five years later.

The Risk Mitigation Independent Power Producer Procurement Programme (RMIPPPP) was launched in August 2020.

In March 2021, the Department of Mineral Resources and Energy announced 8 preferred bidders, including three controversial Karpowership projects proposing floating LNG-fired power stations.

These comprised 450 MW at Richards Bay, 450 MW at Coega and 320 MW at Saldanha Bay – a combined 1,220 MW.

Altogether, RMIPPPP represented 1,418 MW of gas-fired capacity, accounting for more than 70% of the programme’s intended 2,000 MW procurement.

However, the Karpowership projects encountered serious difficulties involving environmental authorisations, port infrastructure, regulatory approvals, and commercial arrangements.

Despite repeated extensions of the financial close deadlines, the projects failed to meet the required legal and commercial milestones.

On 31 December 2023, the final extended deadline expired. Eskom subsequently confirmed that the relevant grid access budget quotes would not be extended further.

The gas-fired projects therefore failed to deliver any electricity under the emergency procurement programme.

The experience highlighted the difficulties of attempting to fast-track large gas-fired generation projects without first securing the necessary infrastructure, environmental approvals, and bankable commercial arrangements.

A new dedicated gas-to-power programme

Meanwhile, the 2019 Integrated Resource Plan for Electricity (IRP 2019) provided for 3,000 MW of new gas-fired generation.

This plan came with a corresponding ministerial determination published in September 2020.

However, it was only on 14 December 2023 that the IPP Office released the RFP for GASIPPPP Bid Window 1 (BW1), targeting 2,000 MW of land-based gas-fired generation.

A further 1,000 MW was envisaged under a separate bid window associated with the Coega industrial development zone. However, repeated extensions followed. 

Prospective bidders raised concerns about fuel-supply arrangements, gas pricing, minimum operating requirements, infrastructure dependencies, and commercial risk allocation.

A substantially revised RFP was eventually issued on 20 October 2025, with the final bid submission deadline extended to 29 May 2026.

Four bids were received: Khanyazwe Flexpower, 440 MW in Mpumalanga; Pictor GTP Consortium, 990 MW in KwaZulu-Natal; Kelvin Redevelopment, 600 MW in Gauteng; and Komatipoort Power, 800 MW in Mpumalanga.

Almost three years after the original RFP was issued, and following extensive amendments and consultations, the procurement process has ended without any capacity being awarded.

The fundamental problem: No assured gas supply

In announcing the outcome on 28 October 2026, the Department of Electricity and Energy acknowledged that bidders were unable to provide gas-supply assurances at the level required by the RFP.

The department noted that South Africa imports most of its natural gas from Mozambique and lacks an operational LNG import terminal.

The department stated unequivocally, “Consequently, no Preferred Bidders were appointed, and no generation capacity was awarded for the GASIPPPP BW1.”

Developers are expected to demonstrate bankable, long-term gas-supply arrangements before South Africa has established the LNG import, storage, regasification, and pipeline infrastructure necessary to support such commitments.

Yet investment in this infrastructure requires confidence that substantial, dependable gas demand will materialise through commercially viable electricity generation projects and other customers.

The result is a circular dependency. Power projects cannot reach financial close without assured gas supplies, while gas infrastructure developers cannot commit billions of rand without assured long-term demand.

This was precisely the interdependency recognised in the original 2015/16 programme, which envisaged coordinated development of LNG import infrastructure and anchor gas-fired power generation.

What happens next?

Ramokgopa has emphasised that government is not abandoning its gas-to-power objectives.

The announcement refers to a possible revision of the procurement process, provisionally described as GASIPPPP BW1.5.

However, no definitive structure, revised procurement requirements or timetable has been announced. 

The government says further information will be provided before the end of 2026.

Meanwhile, the proposed second bid window for 1,000 MW of gas-fired generation at Coega has yet to reach formal competitive procurement.

The IRP 2025 envisages substantial new gas-fired generating capacity to provide flexible and dispatchable electricity.

This is intended to complement increasing contributions from variable wind and solar PV generation.

However, additional capacity allocations in an electricity plan are of little practical value unless they can be translated into bankable projects, affordable electricity, and operational generating capacity.

The need for a different approach

Chris Yelland

The repeated difficulties suggest that amendments to procurement documentation and further deadline extensions are unlikely, on their own, to resolve the underlying problems.

A more coordinated approach may be required, addressing electricity generation, LNG import infrastructure, gas aggregation, transportation, and industrial demand as an integrated programme.

This raises important questions about the respective roles and responsibilities of the government entities involved.

This includes the Departments of Electricity and Energy, Mineral and Petroleum Resources, Forestry, Fisheries, and Environment.

It also includes the National Treasury, the IPP Office, Transnet, the Central Energy Fund, Eskom, the National Transmission Company of South Africa, and private-sector investors.

Equally important is the allocation of commercial risks relating to gas availability, international LNG prices, exchange rates, minimum electricity offtake, infrastructure utilisation, and long-term contractual commitments.

These issues must ultimately be resolved without imposing unacceptable costs and risks on electricity consumers, taxpayers or government.

Furthermore, the economic case for gas-fired generation needs to be evaluated against alternative technologies.

This includes battery energy storage, pumped storage, demand response, and other sources of flexible electricity supply.

Gas-fired generation may have a useful role in providing flexibility and system adequacy. 

However, the extent of this role, its cost and its emissions implications require transparent evaluation within South Africa’s evolving electricity market.

Eleven years and still no delivery

Energy and Electricity Minister Kgosientsho Ramokgopa

The original 2015/16 procurement initiative targeted 3,000 MW but never proceeded to competitive bidding.

The 2020/21 emergency procurement programme selected 1,418 MW of gas-fired projects that failed to reach financial close and deliver electricity.

The dedicated GASIPPPP, launched in December 2023, sought 2,000 MW in its first bid window but has now concluded without a single preferred bidder.

This does not mean that South Africa has no gas-fired generating capacity. 

Existing facilities, including Eskom’s Ankerlig and Gourikwa open-cycle gas turbine plants, and the Avon and Dedisa IPP OCGTs, were procured under earlier programmes and operate primarily using diesel.

Rather, it demonstrates that successive attempts over the past decade to establish new natural-gas-fired IPP generation have failed to deliver operational capacity.

It calls for a fundamental reassessment of the institutional coordination, infrastructure development, risk allocation and procurement model underlying South Africa’s gas-to-power strategy.

After 11 years of announcements, procurement initiatives and missed opportunities, South Africa needs more than another gas-to-power bid window. 

It needs a credible, coordinated and commercially viable implementation strategy that can finally translate policy ambitions into electricity delivered to the grid.

This is an opinion piece written by EE Business Intelligence managing director Chris Yelland.