The government spent R1.82 billion and 9 years building a hospital that was supposed to cost R250 million and take three years to complete
Commenced in 2017, the construction of the Siloam Hospital project in Limpopo has cost South Africa’s Department of Health R1.82 billion to date.
This means the department has spent 94.89% of this project’s approved budget, with completion expected in February 2027.
This new hospital is intended to replace the existing Siloam Hospital in Limpopo, which was built in the 1940s and urgently needed repair.
Former President Jacob Zuma announced the project in 2011, saying it would cost R250 million and take three years to complete.
The government’s updated expenditure on Siloam Hospital was revealed by Health Minister Aaron Motsoaledi in response to a Parliamentary question from National Assembly member Faith Muthambi.
Muthambi had asked the minister about the current status of Siloam Hospital, which has been under construction “for some time now”.
In response, Motsoaledi said the project is expected to realise “small savings against the project budget”.
He explained that the project budget was R1.92 billion, but project expenditure to date has been R1.82 billion.
At completion, he said the total expenditure is expected to be R1.917 billion, which would put the project slightly under budget.
Motsoaledi did not acknowledge that, when Zuma first announced the project, R250 million was pledged to replace the old Siloam hospital over a three-year period.
This R250 million figure was reiterated by former Limpopo Premier Cassel Mathale in his 2012 State of the Province Address.
It was only in 2014, after detailed architectural planning and site assessments, that the budget was tripled to R750 million.
Phase one of the project was launched three years later, with this same R750 million budget still intact.
However, by the time phase two tenders were awarded in 2022, project estimates had risen to between R1.1 billion and R1.4 billion.
In September 2026, the Limpopo MEC for Finance, Kgabo Mahoa, confirmed that the project was valued at R1.37 billion.
Now, in November 2026, Motsoaledi said the budget had increased to R1.92 billion – 668% more than when the project was announced in 2011.
‘On schedule to date, with no cost overruns’

When Zuma announced the Siloam Hospital project in 2011, he said it would be built in phases over three years.
It has now been 15 years since Zuma made this announcement, and 9 years since phase one started.
Despite this, Motsoaledi said in his response to Muthambi’s question that Siloam Hospital “has remained on schedule to date, with no cost overruns”.
“The Main Hospital is complete, and the Rehabilitation Centre is scheduled for practical completion by 20 October 2026,” the minister said.
“However, a court order halting certain ancillary works, specifically the stormwater attenuation pond, could delay overall project completion.”
Despite saying the project is on schedule, Motsoaledi also said that several clearance permits from various government departments and agencies have been outstanding “for some time”.
These outstanding permits, he said, have delayed completion of Siloam Hospital’s stormwater attenuation pond.
“DWS must issue a water use licence for the attenuation pond, and DFFE must issue an environmental authorisation for the stormwater attenuation pond,” he said.
“In addition, the Department of Public Works has been unresponsive regarding demolition permits for dilapidated buildings at Siloam, which is affecting the contractor’s progress on the external ancillary works.”
Despite these delays, Motsoaledi said Siloam Hospital plans to be fully operational in February 2027.